AUSREO’S FAST DELIVERY AND MANUFACTURING CAPABILITY HELP MAKE A DRAMATIC DIFFERENCE TO THE MELBOURNE SKYLINE.
BUILDER:
MultiplexCLIENT:
Form 700LOCATION:
Southbank, VictoriaSTEEL TONNES:
4,068PREFABRICATION ACCELERATES CONSTRUCTION PROGRAMME
AUSREO prefabricated structural steel columns which enabled Multiplex and Form 700 to pour concrete slabs at record speeds. One level every 4 days!
The team produced high quality shop drawings of the prefabricated elements using their proprietary 5D modelling technology.
CERTAINTY OF DELIVERY
A major challenge was the fast construction of the transfer floor on Level 10. Form 700 required 500 tonnes of reinforcement in just 5 days,
The AUSREO team pulled together to schedule, manufacture and deliver 100 tonnes each day without delay.
SCHEDULING EXPERTISE