Civil and Infrastructure
Off-site prefabrication and Australian milled steel are just a couple of reasons why civil engineering and infrastructure builders choose us.

Services

Australian milled steel
Project Management
Design for Manufacture and Assembly (DfMA)
Estimating
5D Building Information Modelling (BIM)
Auto CAD Scheduling
Prefabrication
Safe (and time saving) Delivery Methods

Projects

Brisbane Airport Link

Highlights
AUSREO, in partnership with principal contractor, Theiss John Holland, formed the BRISREO joint venture to manufacture and supply reinforcing steel for one of Australia's largest infrastructure projects.

What the customer said
"We're very happy with AUSREO's work. Their scheduling has been excellent, the bar bending has been very good... their always up-to-date on the program, and their system of using flat racks has worked out well" - Brian Murray, Senior Project Engineer - AirportLink Project Toombul

Location
Brisbane, QLD

Steel Tonnes
120,000 (including 530,000 coupler bars)

Gullen Range Wind Farm

Highlights
The reinforcement for 73 complex, dome shaped pad footings was scheduled using AUSREO's 5D modelling software. This provided accurate marking plans and identified potential placement issues before material was manufactured and delivered to site. Prefabricated piles helped reduce time and labour on site, and innovative delivery methods helped speed up the project.

What the customer said
"AUSREO's delivery method sped up our fixing process and actually helped the steel fixers complete the project more efficiently and on-timel" - Nathan King, Project Manager - CATCON

Location
Crookwell, NSW

Steel Tonnes
3,500

Melbourne Airport Control Tower

Highlights
The 79m tower was constructed using a slipform method of in-situ concrete. AUSREO scheduled and supplied the reinforcement for a continuous concrete pour that lasted 26 hours until the top was reached.

Location
Tullamarine, VIC

Steel Tonnes
240

Epping to Chatswood Rail Link

Highlights
AUSREO manufactured and supplied the reinforcement for 13 km of twin rail tunnels. During tunnel excavation, reinforcing mesh and steel fibre reinforced shotcrete were applied to the crown of the tunnel from a platform at the head of the Tunnel Boring Machine to secure unstable strata and make safe.

Location
Epping to Chatswood, NSW

Steel Tonnes
10,000

Cotter Dam Elargement

Highlights
The Enlarged Cotter Dam is recognised as the largest roller compacted concrete (RCC) dam and the third largest concrete gravity dam in Australia. The reinforcement for this major infrastructure project was supplied by AUSREO.

Location
South Canberra, ACT

Steel Tonnes
2,600

Great Western Highway Upgrade

Highlights
Great Western Highway Upgrade involved the conversion of a 2.9 km section of two-lane roadway to a four-lane divided road with a raised central median, bus zones and enhanced pedestrian/bicycle facilities. AUSREO manufactured and supplied the reinforcing steel.

Location
Lawson, NSW

Steel Tonnes
650

John Gorton Drive

Highlights
Construction of John Gorton Drive is to provide access to the future Molonglo Centre and a smaller centre site to the north for road vehicles and to accommodate on road cycling and future Inter-town Public Transport (IPT). Reinforcement supplied by AUSREO.

Location
Coombs, ACT

Steel Tonnes
700

NCIG Coal Terminal

Highlights
AUSREO supplied reinforcing steel for the greenfield Newcastle Coal Infrastructure Group (NCIG) Coal Export Terminal (CET).

Location
Newcastle, NSW

Steel Tonnes
715

South Western Rail Line and Southern Flyover Project

Highlights
Over a 24 month period, AUSREO supplied reinforcing steel and prefabricated cages to the Glenfield Junction Alliance for completion of the South Western Rail Line and Southern Flyover Projects

Location
Glenfield, NSW

Steel Tonnes
1,490